Future Interstate 343 Oklahoma

Overview

The Oklahoma Department of Transportation submitted an application to the American Association of State Highway and Transportation Officials (AASHTO) for the establishment of Interstate 343 along the Muscogee Turnpike, between Broken Arrow and Webber Falls, on October 6, 2025. The request was approved by the Route Numbering Committee at the Fall 2025 Meeting in November.

The Muscogee Turnpike joins the Tulsa area with Muscogee and the Interstate 40 corridor. The proposed route for I-343 overlays all 52.32 miles of the toll road.

The Oklahoma Turnpike Authority (OTA) and the Indian Nation Council of Governments (INCOG) previously requested to the Oklahoma Transportation Commission (OTC) for the redesignation of the Muscogee Turnpike as Interstate 343 at the Commission Meeting held on May 5, 2025. Approval was recommended by the OTA (Oklahoma Transportation Commission, 2025, Agenda Item 64).

Mileage by State

Oklahoma52.31 mi

Data Sources

December 31, 2021 Interstate Route Log and Finders List

History

1969 Road Map of Northeastern Oklahoma
The Muskogee Turnpike opened to traffic in 1969.

The Muskogee Turnpike was scheduled to open on August 1, 1969. The OTA built the toll road southeast from SH 51 near Broken Arrow to the Muskogee East Industrial Bypass at Hyde Park Road. The turnpike resumed south from Hancock Avenue to Interstate 40 near Webber Falls (Big Basin Herald, 1969a). The Muskogee East Industrial Bypass was constructed by the Oklahoma State Highway Department, and was not ready for traffic by August 1, 1969. The department indicated that two lanes of the bypass would open on August 22, 1969, and until that time, the southern section of the turnpike was inaccessible. As such the OTA committed to opening as much as possible that month (Big Basin Herald, 1969b).

The Muskogee Turnpike finally opened to traffic on October 16, 1969. Construction of the 53.1 mile long toll road was financed by a $32.3 million bond issue (The Oklahoman, 2012). The toll rate was 60 cents at the SH 51 toll plaza to the north and 40 cents at the plaza south of Muskogee. The toll road construction included the Turnpike Concession (service) area at mile marker 25 (Big Basin Herald, 1969a).

North End Oklahoma State Highway 351 Oklahoma State Highway 364 SH 51 ‐ Broken Arrow, OK

Oklahoma State Highway 51 East at Oklahoma State Highway 351

SH 51/Broken Arrow Expwy East at SH 351/Muskogee Tpk

SH 51 shifts southward onto an arterial route paralleling the Muskogee Turnpike to Coweta. The Muskogee Turnpike enters a cloverleaf interchange with SH 364 (Creek Turnpike) nearby. 07/10/26

Oklahoma State Highway 364 East at Oklahoma State Highway 351

SH 364/Creek Tpk East at SH 351/Muskogee Tpk in Broken Arrow, OK

A collector distributor roadway separates along SH 364 (Creek Turnpike) eastbound for SH 351 southeast to Muskogee and northwest to the Broken Arrow Expressway. 07/12/26

Oklahoma State Highway 364 West at Oklahoma State Highway 351

SH 364/Creek Tpk East at the cloverleaf interchange with the Muskogee Tpk

The c/d roadway for the ramps to SH 351 west to the Broken Arrow Expressway (SH 51) and the Muskogee Turnpike southeast to Muskogee partitions from SH 364 westbound. 07/11/26

South End Interstate 40 Oklahoma State Highway 351 ‐ Webbers Falls, OK

Oklahoma State Highway 351 East at Interstate 40

SH 351/Muskogee Tpk East at IH 40 near Webber Falls, OK

The Muskogee Turnpike concludes at IH 40, 0.75 miles south of U.S. 64. 07/10/26

Interstate 40 West at Oklahoma State Highway 351

IH 40 West at SH 351/Muskogee Turnpike near Webber Falls, OK

Interstate 343 will branch northwest from IH 40 at Exit 286 to Muskogee and Tulsa. 07/10/26

Interstate 40 East at Oklahoma State Highway 351

IH 40 East at SH 351/Muskogee Tpk near Webber Falls, OK

There are no exits along the Muskogee Turnpike westbound between IH 40 at Exit 286 and SH 165 in Muskogee, a distance of 19.0 miles. 07/10/26

References

Oklahoma Transportation Commission (OTC). (2025, May 5). Agenda for the Transportation Commission meeting. Oklahoma Department of Transportation (ODOT). Retrieved August 7, 2026 from https://oklahoma.gov/content/dam/ok/en/odot/about-us/transportation-comission/agenda/2025/r/tc_agenda-202505.pdf
New Muskogee Turnpike to Have August Opening. (1969, July 10). Big Basin Herald.
New Muskogee Turnpike Has August Opening. (1969, July 3). Big Basin Herald.
Oklahoma Turnpikes. (2012, September 23). The Oklahoman.